Skip to main content

Operator Efficiency

Displaying operator efficiency list

When to use:

Used when you want to see a list of the task results for completed tasks.

Users:

Manager

Screen Images:

01_1_display_operator_efficiency_list

Detail Specifications:

  • For completed tasks, a list of results can be viewed for each task. This applies to grow operation tasks and maintenance tasks.
    • TASKS: Show the task performed.
    • START TIME: Show the time when the task was started.
    • END TIME: Show the time when the task was completed.
    • DURATION: Show the time taken to perform the task.
    • LOCATION: Show the location where the task was performed.
    • CROP: Show the crop for which the task was performed. Only displayed if the task is a grow operation task.
    • SEED: Show the seed used in the target grow plan. Only displayed if the task is a grow operation task.
    • QUANTITY/WEIGHT: Show the quantity or weight, or both, entered as actuals. Only displayed if the task is a grow operation task.
    • ASSIGNEE: Show operator who performed the task.

Filtering operator efficiency list

When to use:

Used to filter the list of operator efficiency to be displayed.

Users:

Manager

Screen Images:

05_1_display_operator_efficiency_filter

Screen after clicking
05_2_operator_efficiency_filter_popup

Detail Specifications:

  • You can narrow down the list of results by clicking on the “Filter” button in the upper right corner of the screen.
  • The criteria for narrowing down the list are as follows. Set what you want to filter by and click the “Save” button.
    • Assignee
    • Location
    • Date: The target data must be completed between the start and end dates.
    • Crop
    • Seed
    • Task
  • Multiple criteria can also be crossed to narrow down the search.

Export CSV of operator efficiency list

When to use:

Used when you want to export the list in CSV.

Users:

Manager

Screen Images:

02_1_export_csv

Screen after clicking
02_2_export_csv_popup

Detail Specifications:

  • Click the "Export CSV" button in the upper right corner of the screen to start downloading operator efficiency list in CSV.
    • Data that apply to the filtering conditions applied in the list screen will be output.
  • On the pop-up screen, you can specify the period of time for which you want to output data.
    • If no period for output is set, data for results completed in the last 30 days will be output.

Task Estimation Time

Displaying the task estimation time list

When to use:

It is used to check each user's task estimation time settings.

Users:

Manager

Screen Images:

Screen transition 03_1_set_task_estimation_time

List view 03_2_task_estimation_time_list

Detail Specifications:

  • Click the "Set Task Estimation Time" button in the upper right corner of the Operator Efficiency List screen to move to the Task Estimation Time list screen.
  • By selecting the user you want to check from the list of users on the left side of the screen, the current settings are displayed on the right side of the screen.
  • For tasks based on cultivation plans, estimated time is set for each crop. By selecting the name of the crop, you can see the estimated time for that crop.

Edit task estimation time

When to use:

It is used to edit the task estimation time settings for each user.

Users:

Manager

Screen Images:

Screen transition 04_1_task_estimation_time_list_edit

Edit view 04_2_task_estimation_time_list_edit

Detail Specifications:

  • Users who checked the checkbox on the "Task Estimation Time List" screen are eligible to edit.
  • The initial display of this screen depends on the number of users to be edited.
    • If there are multiple users to be edited, the owner's default value will be displayed.
      caution
      • The owner's default value is not changed even if the value is changed here and saved.
    • If the user to be edited is singular, the current setting values of the corresponding user will be displayed.
  • If the task is based on a cultivation plan, the estimated time is set for each crop. By selecting the name of a crop, you can view and edit the estimated time for that crop.
    tip
    • It is also possible to apply changes to the estimated time for each crop in a batch.
    • Please make the settings on the batch application screen that appears after clicking the "Set Multiple Crop Types" button.
  • You can exit the edit mode by clicking the "Cancel" button.